Systems

Fire protection over the primer: a four-coat order that cannot be reversed

Rework on structural fire protection is rarely caught on acceptance day. An intumescent coating looks flat, measures to thickness and matches the colour; every box on the form can be ticked. The failure shows up after one thermal cycle — lifting, hollow spots, sheets coming away — usually a year after completion. At that point the argument is not technical but contractual: the fire-protection crew says the primer let go, the coatings crew says the intumescent pulled it up, and both explanations hold.

The accepted sequence is anticorrosive primer, anticorrosive intermediate, intumescent, anticorrosive topcoat — four coats, not interchangeable. The intermediate must sit under the intumescent to control the thickness of the coats below, so they do not deform at high temperature and push the fire layer off; adding thickness 'for safety' works in the opposite direction here. The topcoat must sit above the intumescent because a hard, thick film over an intumescent stops it foaming, and the fire rating survives only on paper.

Compatibility is where projects actually fail. Both the intumescent and the anticorrosive are organic, and the manufacturer should issue a written compatibility statement against the specified primer; without one, a third-party test or a site trial panel is required, built with realistic intercoat intervals rather than next-day application. On zinc-rich primers, zinc salts must be removed and the primer fully cured — tack-free is not cured — and a tie coat may be needed. Put the compatibility clause and the trial panel into the contract and the quotation; both cost little compared with stripping a fire layer off structural steel. For export shipments, add the condensation and zinc-salt risk in transit to the handover documents.

Need selection advice?

Tell us your substrate and service conditions

One-to-one coating consultancy: system design, quantity take-off and quotation.

Contact us