Coating lead time is three stages, not one number

When a coating schedule slips, six times out of ten it is not the paint quality — it is paint that has not arrived. And the most awkward version of that: contract signed, money paid, factory says it is in the production queue.

To be useful, this has to start with an admission: coating lead time was never one number. It is three stages stacked together, and skipping any one of them turns into waiting on site.

1. What the three stages are

Stock: is this grade on the shelf. Stocked grades ship in 1–3 working days; grades pulled from the manufacturer usually take 5–10; imported or special items follow factory scheduling, and 3–4 weeks is normal.

Colour: standard references (RAL, BS, Munsell) usually map to stock or fast production. Non-standard colours need a match, approval and then scheduling — and that stage is often longer than the stock stage. Many projects forget it entirely and discover at dispatch that the colour was never confirmed.

Transport: coatings are dangerous goods. Road movement needs a licensed vehicle, sea freight needs dangerous goods packing certification and an SDS, air is largely out. Time here depends not on distance but on whether compliant capacity and complete paperwork exist.

So the right way to ask 'how long' is: is the grade stocked, is the colour standard or matched, where is it going, road or sea. Without those four answers, any lead time is a guess.

2. Stocked versus pulled from the factory

Stock means more than speed — it means splittable. For products sold in full kits, stock lets you take the quantity you actually need and top up if the site miscalculated. A factory pull means buying the manufacturer's minimum pack, with the balance sitting in your warehouse.

That is why the same grade can carry lead times two weeks apart from different suppliers: one holds stock, one does not. The test is simple — ask which city the stock is in and roughly how much. A supplier who cannot say is pulling from the factory.

3. Colour is what kills the schedule

A real case: a yard needed 200 litres of a dark grey topcoat matched to a sample supplied by the owner. It looked like a small order and took three weeks — sample to the factory, match, sample back, approval, then a visible difference against the original batch, and a re-match.

The fix is not complicated: settle colour at project start rather than at the point of use. Prefer a standard reference; if it must be a sample match, allow at least two weeks and agree in advance what colour difference is acceptable, otherwise approval loops.

4. Building a delivery plan that does not rework

Sequence backwards from the application order instead of shipping the total quantity at once. Primer first, intermediate next, topcoat last — topcoat colour and gloss are the most rework-prone, and arriving early only occupies space and shortens shelf life.

Each delivery needs inspection time: open a pail for settlement or skinning, check batch and production date, confirm the hardener ratio. That is half a day to a day, and it is not part of 'arrived, therefore ready'.

One counter-intuitive suggestion: on critical projects, do not put the entire quantity in one batch. Ship two — the first for a trial area or first section to verify system and colour, the second adjusted to what the trial showed. The cost is one extra freight; the benefit is avoiding a full rework.

5. What belongs in the contract

Do not write only 'delivery within X days of signing'. Break it into three milestones: stock confirmation, colour approval, dispatch. Say who owns each and what happens on overrun.

Add two clauses. One: delay caused by colour approval does not count as supplier default — this protects both sides and stops a supplier rushing a match to avoid liability. Two: on split deliveries, each batch is inspected and paid separately — which gives the site an incentive to call off in application order rather than stockpiling.

The most practical clause of all: put a shippable date on every line of the quotation. Not 'as soon as possible' but a date. Where it cannot be met, say so — that is far less work than explaining afterwards.