Seven days in dock: sequencing the coating work backwards

Dock planning is never 'fit the work in'. It is identifying which steps cannot be compressed and only then optimising the rest. Coatings typically occupy 40–60% of the critical path: done well that saves two days, done badly it costs a week.

1. Mark the chain that cannot break

High-pressure washing, blasting, primer, intermediate, topcoat — each step waits for the previous to reach a recoatable state. What cannot be compressed is the waiting: epoxy primer needs at least 4–6 hours at 20 °C, and double that in the cold.

What can run in parallel is zoning. Split the hull into blocks: blast A while priming B and topcoating C, rotating crews and equipment to absorb the waiting. It is the only reliable way to finish early, at the cost of much harder scheduling.

What cannot run in parallel is antifouling. It goes last, with enough drying time before launch; bring it forward and large areas shed on the first voyage.

2. The weather window is not a probability

The commonest planning error is working from historical weather odds. Coatings do not need 'no rain'; they need RH below 85% and steel temperature 3 °C above dew point. Neither condition is guaranteed on a sunny afternoon — steel heats in the sun, sea breeze carries salt, and the dew point margin narrows.

The practical method is to measure morning and afternoon every day, log it, and adjust the day's sequence from the readings rather than forcing the weekly plan. A dew point meter and a surface thermometer on site beat any scheduling software.

3. When the paint reaches the dock

Ideally everything arrives the day before work starts and is inspected. In practice it comes in two batches: primer and intermediate before start, topcoat and antifouling mid-dock — topcoat colour is the item most likely to be changed by the owner, so early arrival is a risk, not a saving.

Watch the storage conditions inside the dock. Paint must not sit in sun, in rain, or next to welding. Space is tight and many projects stack pails in the open; a day in the sun takes drum temperature past 50 °C and noticeably shortens epoxy pot life.

4. The last 24 hours

In the final 24 hours before launch, do three things only: the last antifouling coat, inspection and repair of misses and damage, and cleaning the dock floor. Schedule nothing that needs drying time in that window.

Inspect for misses with a strong light at a low angle, not straight on. Shell butts, scuppers, and the rudder-to-rudder-stock joint are the usual locations. Touch-up there needs longer to dry than on flat plate because ventilation is poor.

5. The three real causes of overrun

Blasting rework: Sa2.5 was assumed in one pass, old paint showed through locally, and the second pass costs a day. Topcoat colour rejected by the owner, whole face redone. Antifouling forced by a tide window, launched early, back in dock.

What they share: all unplanned, and none of them a technical problem — all judgement and communication. Dock management is less about applying paint well than about making the right trade-off at the right moment.